Construction work is well on schedule thanks to the mild winter.
The excavation and pile-driving work has been completed. The floor slabs, walls and ceilings above the basement are currently being concreted. The building will soon gain height and take on more shape.
The building shell will be finished in late autumn 2017. Work on the interior will start afterwards. The moving date is scheduled for summer 2018.