A large portion of the beautiful timber structure for the roof has been erected. And the windows have already been put in. These are two visible steps, but there are countless others that are not noticeable at first glance. Such as the technical preparations for the sprinklers, or the roof water outlet, for example.
Track areas
The substructure for the track areas is complete. We will have two internal tracks, for seven and eight rail wagons, and an external track for eight reserve rail wagons. The «actual» track construction, which will provide a connection to the rail network, will follow in the spring.
Looking ahead: According to plan, the scaffolding will be dismantled at the end of February. In spring, which means towards the end of April, we will then be ready for interior construction – if the weather and especially the temperatures play along.
«Green island» with a home advantage
There is a biotope on our plot of land. Our building project is not allowed to endanger the habitat of the animals living there. That is to say, the biotope has protected status and we have the obligation to preserve it. Economy and ecology in harmony, Eco Balance by CAMION TRANSPORT.
Okay, so when can we move in? As things stand at present, we will be getting the starting signal in September 2023.